News
      
        
          Cementation Canada gets gold
            Cementation Canada was recently awarded  three new projects in a buoyant gold market. 
             Crews are on site at Apollo Gold’s Black  Fox Mine near Matheson, Ontario and Northgate Mineral’s Young-Davidson Mine  near Matachewan, Ontario. Both projects are in North Eastern Ontario and  involve First Nations Agreements. Black Fox Mine is transitioning from open pit  to an underground operation and the scope of work includes underground  development and raise boring. The Young-Davidson project is an engineer,  procure and construct (EPC) contract to deepen an existing shaft and develop a  new production shaft by raise boring. 
           Kitikmeot Cementation Mining &  Development (KCMD) has been awarded the development program at Newmont’s Hope  Bay Project in Nunavut, north of the Arctic Circle. KCMD is a joint venture  between Cementation Canada and Inuit partner, Kitikmeot Corporation of  Cambridge Bay, Nunavut.  | 
          RUC Cementation goes global 
            By extending its focus to markets further  afield, RUC Cementation has recently been able to secure a number of large  international contracts, including: 
            
              -  Construction  of three raise bored shafts of six metres in diameter and 550 metre depth  over three years at Freeport Indonesia on Papua Island
 
              -  Raise  drilling of two shafts to a depth of 1 300 metres at Ivanhoe Mines copper  gold project in Mongolia in what is considered to be the finest copper and gold  ore body in the world
 
              -  A  sub-contract with Gammon Construction for shaft sinking works for a new  sewerage system in Hong Kong
 
             
            
            
              
                | 
             
            
              | Sewerage works in Hong Kong | 
             
          | 
         
        
          Working at extreme depth
           
                
                    | 
                 
                
                  Murray & Roberts Cementation  site  
                  establishment at South Deep Mine | 
                 
            Murray & Roberts Cementation will apply  its experience in mine development to deepen an existing shaft at the Gold  Fields South Deep mine near Carltonville on the West Rand to 3 000 metres. The  shaft is being extended to match the man and materials shaft adjacent to it,  which is currently the deepest rock hoisting shaft in the world. 
            
            This is the latest in a portfolio of  projects Murray & Roberts Cementation is completing for the mine which  includes the new mine development below 95 level. It will be undertaken in a  challenging environment of extreme depth and will require a methodology that  allows safe access below an existing shaft.  | 
           
            Murray & Roberts wins IAS Award
            Murray & Roberts won the Investment  Analysts’ Society (IAS) award for the best presentation to the Society in  2009/2010 for companies with market capitalisation between R5 billion and R20  billion. 
               
            The IAS is a liaison body for the  investment analyst profession. The Society currently has 2 000 members,  including investment banks and houses, fund managers, brokers, insurance  companies and pension funds. 
             
            Each year, the IAS promotes a prestigious  awards ceremony in recognition of the skills of those listed companies that win  awards for “Best Communicating and Reporting”.  | 
         
        
          Concrete Technology
            Murray & Roberts has established a  Concrete Centre of Excellence to raise the level of construction technology in  the Group and introduce new technology to improve efficiency and reduce costs. 
             The centre is based at the Elandsfontein  head office of Murray & Roberts Construction and it serves a number of  group operations that work with concrete. It is managed by Cyril Attwell, a  research scientist and expert in concrete technology who joined the Group when  he was employed to provide advice on the optimal use of concrete for the  Gautrain project. 
             In the six months between January (when it  was established) and June this year, the centre has achieved significant bottom-line  savings for group operations by modifying concrete technology across a broad  spectrum and reducing costs. These savings are reflected in increased margins  on existing projects, enhanced competitiveness in tender negotiations (where  savings of between 10% and 25% are being achieved on concrete costs) and  theoretical savings gained by using alternative concrete mixes. 
           Group operations that are benefiting from  the work of the centre include Hall Longmore, Rocla and the Cementation Group.  The Concrete Centre of Excellence plans to extend its work to other group  operations in future to generate even higher levels of efficiency and cost  saving.  | 
         
        
          
            Iconic Middle East projects near completion            
            
                
                    | 
                 
                
                  |  Sheik Zayed University | 
                 
           
            Murray & Roberts Middle East is making  good progress on a range of projects in Abu Dhabi and Bahrain. 
            The R2,5 billion Paris Sorbonne University  for Mubadala in Abu Dhabi is nearing early completion ahead of the contract  program and within budget. The R6 billion Sheik Zayed University for Mubadala  is also progressing well and has a target completion date of July 2011.  Construction of the complicated space-age roof is underway, and the structure  is taking shape. 
             Work on the new St Regis hotel, resort, and  conference centre on Saadiyat Island in Abu Dhabi is proceeding well and the Al  Habtoor-Murray & Roberts joint venture continues to focus on its commitment  to safety and the highest quality of construction expected by its client, the  Tourism Development and Investment Company. The project is scheduled for  completion in 2011. 
           In Bahrain, the Arcapita Bank headquarters  building and mosque is almost ready for occupation. The building has a  prominent position in Bahrain Business Bay.  | 
         
        
          | 
             Construction of the two chimney structures  for the Medupi power station is well underway. The R1 billion contract, in  which Concor is participating as a joint venture partner, was awarded in April  2009 and involves the design and construction of two chimney structures and the  construction of three coal silos and six fly-ash silos. 
             Design is not often included in a  construction contract and this element of the project will allow the joint  venture to demonstrate its civil engineering capabilities in the design and construction  of these specialised structures. 
             The project is progressing slightly ahead  of schedule as the joint venture partners demonstrate their world class  expertise in chimney sliding. The sliding of the outer casing of the first  chimney windshield was completed in mid-May. It took six weeks, working  continuously 24 hours a day and seven days a week, to slide the first chimney.  The foundation for the second chimney is ready and the sliding of its  windshield is due before the end of the year. 
              
                  | 
               
              
                | Medupi’s first chimney | 
               
             
             The Medupi chimneys will be 220 metres  high with three steel flues per chimney. This is different from the  conventional Eskom chimneys of the past which had brick flues. Installation of  the nine metre diameter steel flues will comprise the next stage of the project.  From an environmental perspective, the two chimneys are flue gas  desulpherisation (FGD)-ready. 
             Construction of the coal and fly-ash silos  has commenced and the first fly-ash silo was slid in July.             
            
            
           | 
          CONCOR PROJECTS
            Bramhoek and Bedford dams
            The contract to construct the Bramhoek and  Bedford dams for the Ingula pumped storage scheme was awarded to the Bramhoek  Dams Joint Venture, of which Concor Roads & Earthworks is the lead  contractor. 
            
              The Ingula pumped storage scheme consists  of an upper dam, Bedford, and a lower dam, Bramhoek. Both will have an  approximate water capacity of 22 million cubic metres. The dams are  4,6 kilometres apart and are connected by underground waterways through an  underground powerhouse which will house four 333MW pump turbines. 
            
              The contractors moved onto site in April  2008 and the scheduled completion date for Bramhoek Dam is October 2010 with  its impoundment in August 2010. Bedford Dam is scheduled for completion early  in 2011. 
            
              The site of the pumped storage scheme spans  the Little Drakensberg, straddling the provincial boundary of the Free State  near Harrismith and KwaZulu Natal, near Ladysmith. 
            
    
                
                    | 
                 
                
                  | Bramhoek dam | 
                 
            | 
         
        
          Concor Mining extracts bulk coal sample for Sasol’s  Mafutha project
            Concor Mining secured the contract for the  excavation of the bulk coal sample for the Sasol project, and coaling of this  bulk sample was completed in the first quarter of 2010. The project is situated  at Steenbokpan, near Lephalale in Limpopo Province, and site establishment took  place in July 2009. 
             Sasol requires the bulk coal sample for  large scale gasification trials in one of Sasol Synfuels’ gasifiers in Secunda  as part of its pre-feasibility study into the establishment of a potential  coal-to-liquids (CTL) plant in the Lephalale area. 
             The contract entails the removal of top  soil, then overburden to a depth of 34 metres and the extraction of a  selected coal sample to a depth of 91 metres.  
             The project is particularly complicated as  the mining area has been kept to a minimum and the coal has to be selectively  drilled and blasted, and then mined. 
            
              
                  | 
               
              
                | Excavation of the coal bulk sample | 
               
             
 | 
          Concor building wins SAPOA 2010 award
            The Department of International Relations  and Co-operation’s new office and conference centre development in Tshwane, of  which Concor Building was the main contractor, won the prestigious South  African Property Owners Association (SAPOA) 2010 awards in the best development  and best overall property development categories. 
              The R1,2 billion building structure  embodies a functional and efficient use of space for staff and the public which  is further enhanced by high standards of green design principles. 
              Accommodating some 2 500 employees  with 1 500 parking bays, the 138 570 cubic metre building includes a state  of the art conference facility designed to house the African Union and South  African Development Community (SADC) conferences.  
           
            
                
                    | 
                 
                
                  | Front façade of the building | 
                 
            | 
         
        
          Precision and safety
            
              
                  | 
               
              
                |  Medupi Heavy Lift | 
               
             
            A major lift of 1 160 tons undertaken in July  2010 to erect the roof of the first Medupi boiler used a method called strand  jacking to ensure the highest levels of precision and safety. The process  involved the lifting of a heavy steel grid that will house the boiler onto a  104 metre high steel frame. 
             Strand jacking is a construction process in  which large construction elements such as concrete slabs and steelwork are  lifted into position with computer-controlled hydraulic jacks. Because the  multiple jacks can be moved in unison and with great precision, heavy  structures can be assembled at ground level and then lifted into position  rather than being built at higher levels. This allows for increased safety and  it reduces costs. 
             The Medupi heavy lift was successfully  completed with support from Swiss subcontractor, Hebetec Engineering Limited,  and Murray & Roberts company, Freyssinet. The transfer of valuable skills  during the process will ensure that Murray & Roberts is able to complete  the process for the other Medupi boilers. 
           | 
          Ngqura harbour container terminal phase II
             Concor continues its involvement in the  construction of South Africa’s newest deep water harbour. The Hochtief-Concor  Joint Venture is currently constructing the Phase II expansion of the Ngqura  Harbour Container Terminal.
 
              The Ngqura Container Terminal, which opened  in 2009, is attracting increasing volumes of container traffic, and requires  expansion of the quay from two berths to three. 
              On completion of the quay wall, the dry  excavation, in which it is built, was flooded allowing the sea to engulf the  seaward face of the wall.
               
              
          Construction of the container terminal is  on schedule for handover in February 2011.  | 
         
       
 |